Bhogapuram Airport Project Delayed Due To Lack of Coordination

While the Bhogapuram International Airport has been much talked about, VUDA is still awaiting the go-ahead for developing the layout of a residential housing complex under the Bhogapuram Airport project.

The Bhogapuram Airport is proposed to be developed at a cost of Rs 2461.27 cr at 2558 acres of land close to the Bay of Bengal. The airport will include a new runway, terminal building, apron, air traffic controller building and more. It is expected to cater to big aircrafts, including the Airbus A-380.

Two weeks ago, orders were reportedly issued by the Vizianagaram district administration and the authorities concerned, but the revenue department of Vizianagaram and Bhogapuram International Airport Corporation Limited (BIACL) are yet to give the go-ahead. The main reason behind the delay is touted to be the lack of coordination between the authorities concerned.

VUDA officials are also yet to receive from Vizianagaram authorities and BIACL information regarding the area of the layout and nature of these houses. “Without cooperation from the stakeholders, we cannot go ahead with the project. Besides, no money has been allocated to us to take up for the layout design,” a VUDA official reportedly said.

But the Vizianagaram Collector Vivek Yadav has reportedly said they’ll soon be handing out the information required to VUDA. 376 beneficiaries have been identified for the housing project, with each beneficiary getting 5 cents of the plot. The housing project is expected to come up in a few other areas of Bhogapuram, including Polipalli.

VUDA has reportedly been also asked to complete the layout design by six months. “I will soon meet Vuda vice-chairman T Baburao Naidu to discuss the project. This apart, there will be another meeting with the beneficiaries to decide what type of houses they want in the residential layout

,” he said.

The district revenue authorities are supposed to hand over 2558 acres of land to BIACL but only 1402 acres of government and private land has been assigned. Within a week, officials are touted to keep 695 acres of more land ready for BIACL.

 

This post was last modified on 05/04/2017 1:02 pm

Leave a Comment
Published by
Team Yo! Vizag

Recent Posts

EKA Mobility gets contract for 750 electric buses in Andhra; 100 buses in Visakhapatnam

In a major push toward sustainable public transport, EKA Mobility has secured a contract to…

8 hours ago

10 hottest new OTT releases dropping today to end your week with a bang!

There are a variety of new movie and web series releases today on our favourite…

9 hours ago

Top-rated thrilling alien-centered movies and series to stream this weekend!

The survival trope in movies and television shows is one of the popular genres, attracting…

11 hours ago

Who is the Mayor & how is this position different from others?

For months now, the mayor’s chair in Visakhapatnam has been making headlines. From no-confidence motions…

11 hours ago

Naked thief caught on CCTV camera in Visakhapatnam

In an incident that has left residents unnerved, a "naked thief" was caught on CCTV…

13 hours ago

Sleeper-Class Visakhapatnam-Bengaluru Vande Bharat demanded

Kanchumurthi Eswar, a member of the Zonal Railway Users’ Consultative Committee (ZRUCC), has urged Divisional…

14 hours ago